WSP : Construction Progress Report from Water System and Public Latrine [January 19, 2022]

in STEEM FOR BETTERLIFE3 years ago
Note: 50% of Rewards to accelerate the construction of the Water System and Public Latrine @worldsmile account

poster_2022-01-19-032747.png

Construction Progress Report from Water System and Public Latrine

Today is January 19, 2022, Of the 11 main works on the construction of the Water System and Public Latrine, three works have been completed and two are in progress. Three jobs that have been completed are Bouwplank, Footing and Sloof. While the two works being carried out are Column and Wall, where the main column work for all the steel has been installed and the other has been wrapped with formwork which has been filled with concrete.

For the wall today being worked on at the latrine point, where the estimated time for these two works that are being worked on will be completed in the next four days, the other main work after completion of the columns and walls to be worked on is the top beam and floor which will start with earth filling.

For analysis of construction techniques from the Water System and Public Latrine per day it has reached 18% this happens because the work items are 11 and can be categorized by separating each work item itself. For more details, you can see as in the table and the current condition of each work on the construction as below.

Table of the main types of work from the construction of the Water System and Public Latriner
NumberType of workNotes
1.BouwplankComplete
2.FootingComplete
3.SloofComplete
4.ColumnAlmost complete
5.WallAlmost complete
6.BeamOn Progress
7.FloorOn Progress
8.Water tubOn Progress
9.RoofOn Progress
10.PaintingOn Progress
11.ElectricalOn Progress
Design of Water System and Public Latrine Construction
image.png
Progress of Water System and Public Latrine Construction
PerspectivePresent Condiition
Front View20220119_142014.jpg
Front and Right View20220119_142031.jpg
Front and Left View20220119_141958.jpg
Right View20220119_142047.jpg
Left View20220119_141942.jpg
Back View20220119_141859.jpg
Back and Right View20220119_142101.jpg
Left and Right View20220119_141919.jpg

This is a construction report related to the construction of the Water System and Public Latrine to all donors of the World Smile Project, especially to the steemit team through @steemcurator01 and @steemcurator02 who have provided support so far, I have done this construction report in accordance with technical analysis prevailing in Indonesia.

MAIN INFORMATION FROM WORLD SMILE PROJECT
Project NameWater System and Public Latrin
BeneficiaryKumbang Village Community
AddressSyamtalira Aron, North Aceh - Indonesia
Mapwhat3words.com

Related Links


Note:


  • Construction progress reports are in accordance with technical analysis
  • Financial Report will be submitted by other WSP team
  • All documents have been authorized by the relevant parties
  • Documents in the form of photos or writing must have permission from World Smile Project team

Cc : @pennsif @el-nailul @heriadi @irawandedy @miftahuddin @sofian88 @mariana4ve

Thanks
@klen.civil


cropped_image (1).png

Sort:  

@tipu curate

I admire your dedication to supporting others in their development

 3 years ago 

Wow.. Day by day it increases the project fast.

Praying to all kindhearted behind this project may the God of heaven fullfil all your dreams in life🙏🙏❤️

 3 years ago 

Thanks

 3 years ago 

I am so proud of you and this community, may God continue to strengthen you all

 3 years ago 

Thanks

 3 years ago 

Super

 3 years ago 

Thanks

 3 years ago 

It's Nice seeing the progress. Keep it going.

 3 years ago 

Thanks

 3 years ago 

It is amazing to see that the project is moving smoothly. Well done team!

 3 years ago 

Thanks

 3 years ago 

I know it will finish soon sir. Great job

 3 years ago 

Gran labor equipo!!!

 3 years ago 

This is also thanks to the support of the WSP VE team

😉