WSP : Construction Progress Report from Water System and Public Latrine [January 19, 2022]
Today is January 19, 2022, Of the 11 main works on the construction of the Water System and Public Latrine, three works have been completed and two are in progress. Three jobs that have been completed are Bouwplank, Footing and Sloof. While the two works being carried out are Column and Wall, where the main column work for all the steel has been installed and the other has been wrapped with formwork which has been filled with concrete.
For the wall today being worked on at the latrine point, where the estimated time for these two works that are being worked on will be completed in the next four days, the other main work after completion of the columns and walls to be worked on is the top beam and floor which will start with earth filling.
For analysis of construction techniques from the Water System and Public Latrine per day it has reached 18% this happens because the work items are 11 and can be categorized by separating each work item itself. For more details, you can see as in the table and the current condition of each work on the construction as below.
Number | Type of work | Notes |
---|---|---|
1. | Bouwplank | Complete |
2. | Footing | Complete |
3. | Sloof | Complete |
4. | Column | Almost complete |
5. | Wall | Almost complete |
6. | Beam | On Progress |
7. | Floor | On Progress |
8. | Water tub | On Progress |
9. | Roof | On Progress |
10. | Painting | On Progress |
11. | Electrical | On Progress |
Perspective | Present Condiition |
---|---|
Front View | |
Front and Right View | |
Front and Left View | |
Right View | |
Left View | |
Back View | |
Back and Right View | |
Left and Right View |
This is a construction report related to the construction of the Water System and Public Latrine to all donors of the World Smile Project, especially to the steemit team through @steemcurator01 and @steemcurator02 who have provided support so far, I have done this construction report in accordance with technical analysis prevailing in Indonesia.
Project Name | Water System and Public Latrin |
---|---|
Beneficiary | Kumbang Village Community |
Address | Syamtalira Aron, North Aceh - Indonesia |
Map | what3words.com |
Related Links
WSP : Construction Progress Report from Water System and Public Latrine [January 15, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 11, 2022]
Note:
- Construction progress reports are in accordance with technical analysis
- Financial Report will be submitted by other WSP team
- All documents have been authorized by the relevant parties
- Documents in the form of photos or writing must have permission from World Smile Project team
Cc : @pennsif @el-nailul @heriadi @irawandedy @miftahuddin @sofian88 @mariana4ve
Thanks
@klen.civil
@tipu curate
I admire your dedication to supporting others in their development
Upvoted 👌 (Mana: 5/7) Get profit votes with @tipU :)
Wow.. Day by day it increases the project fast.
Praying to all kindhearted behind this project may the God of heaven fullfil all your dreams in life🙏🙏❤️
Thanks
I am so proud of you and this community, may God continue to strengthen you all
Thanks
Super
Thanks
It's Nice seeing the progress. Keep it going.
Thanks
It is amazing to see that the project is moving smoothly. Well done team!
Thanks
I know it will finish soon sir. Great job
Gran labor equipo!!!
This is also thanks to the support of the WSP VE team
😉