WSP : Construction Progress Report from Water System and Public Latrine is Done 100% [February 22, 2022]

in STEEM FOR BETTERLIFE3 years ago
Note : 50% of this post payout is for world smile project program (@worldsmile)
poster_2022-02-22-050603.png
Construction Progress Report from Water System and Public Latrine

After being done some time ago, now I as the construction supervision team for the water system and public latrine report specifically to all donors and other steemit users that this construction was right on Tuesday, February 22, 2022, the workers had finished working on it, this is in accordance with technical analysis construction. And we from the WSP team also say a thousand thanks to all donors who have shared with WSP so that this project is completed perfectly.

All forms of work items and 100% progress conditions for donors and other steemit users can see the work item table and photo table as below.

Table of the main types of work from the construction of the Water System and Public Latriner
NumberType of workNotes
1.BouwplankComplete
2.FootingComplete
3.SloofComplete
4.ColumnComplete
5.BeamComplete
6.WallComplete
7.FloorComplete
8.Water TubComplete
9.RoofComplete
10.PaintingComplete
11.Electrical and Water SystemComplete
Design of Water System and Public Latrine Construction
image.png
Progress of Water System and Public Latrine Construction
PerspectivePresent Condiition
Front View20220222_162522-01.jpeg
Front and Right View20220222_162324-01.jpeg
Front and Left View20220222_162100-01.jpeg
Right View20220222_162306-01.jpeg
Left View20220222_162126-01.jpeg
Back and Right View20220222_162153-01.jpeg
Back and Left View20220222_162246-01.jpeg
Water Tub20220222_162428-01.jpeg
Faucet20220222_162417-01.jpeg
Latrine20220222_162351-01.jpeg

This is a construction report related to the construction of the Water System and Public Latrine to all donors of the World Smile Project, especially to the steemit team through @steemcurator01 and @steemcurator02 who have provided support so far, I have done this construction report in accordance with technical analysis prevailing in Indonesia.

MAIN INFORMATION FROM WORLD SMILE PROJECT
Project NameWater System and Public Latrin
BeneficiaryKumbang Village Community
AddressSyamtalira Aron, North Aceh - Indonesia
Mapwhat3words.com

Note:


  • Construction progress reports are in accordance with technical analysis
  • Financial Report will be submitted by other WSP team
  • All documents have been authorized by the relevant parties
  • Documents in the form of photos or writing must have permission from World Smile Project team

Cc : @pennsif @el-nailul @heriadi @irawandedy @miftahuddin @sofian88 @mariana4ve @bien

Thanks
@klen.civil


cropped_image (1).png

Sort:  

Wow, this is the best project i have seen directly affecting life's of Human in an unprecedented way. thanks to word smile for this initiative. kudos.

 3 years ago 

Гениально!

 3 years ago 

Thanks

 3 years ago 

Wow, finally. Congragulations and thanks to worldsmile for this great deeds.

 3 years ago 

Thanks bro

 3 years ago 

Thanks

 3 years ago 

It's very nice. Health for your labor 🙏

 3 years ago 

Thanks

 3 years ago 

Thank you so much for supporting the World Smile Project Program by appointing @worldsmile as a beneficiary.

Your post has entered the List of Posts that Support the World Smile Project with 50% Share Rewards | 23/02/2022

 3 years ago 

Pekerjaan bagus steem amal desa kumbang ka selesai 😀
#club100

Hey there! I stumbled upon this post and just wanted to say congrats on getting the Water System and Public Latrine project done 100%! That's awesome news! I'm new to this forum, so forgive me if I'm a little late to the party. It's great to see the nuts and bolts of the construction process and all the different types of work that went into it. And it's even better to see that everything is complete and up and running. Kudos to the WSP team and all the donors who helped make this project a success. LMK how it's going.