WSP : Construction Progress Report from Water System and Public Latrine [February 13, 2022]
The achievement of construction progress from the water system and public latrine right on today, February 13, 2022, has reached 85%, where of the 11 construction work items from this construction, only 3 main work items are being worked on, on average the work items are being worked on, both separately or at the construction site. The roof of the building is already at the painting stage in the welding workshop while other work items carried out at the construction site are finishing painting and installing clean water installations. Meanwhile, the electrical installation will be carried out after the roof is installed on the building.
This is the achievement of the construction progress of the water system and public latrine which has reached 85%, to be clear about the condition of this progress, donors and other steemians can see the work item table and the current condition table of the water system and public lantrine construction such as below this:
Number | Type of work | Notes |
---|---|---|
1. | Bouwplank | Complete |
2. | Footing | Complete |
3. | Sloof | Complete |
4. | Column | Complete |
5. | Beam | Complete |
6. | Wall | Complete |
7. | Floor | Complete |
8. | Water Tub | Complete |
9. | Roof | Almost Complete |
10. | Painting | Almost Complete |
11. | Electrical and Water System | Almost Complete |
Perspective | Present Condiition |
---|---|
Front View | |
Front and Right View | |
Front and Left View | |
Right View | |
Left View | |
Back View | |
Back and Right View | |
Back and Left View | |
Water Tub | |
Latrine | |
Roof |
This is a construction report related to the construction of the Water System and Public Latrine to all donors of the World Smile Project, especially to the steemit team through @steemcurator01 and @steemcurator02 who have provided support so far, I have done this construction report in accordance with technical analysis prevailing in Indonesia.
Project Name | Water System and Public Latrin |
---|---|
Beneficiary | Kumbang Village Community |
Address | Syamtalira Aron, North Aceh - Indonesia |
Map | what3words.com |
Related Links
WSP : Construction Progress Report from Water System and Public Latrine [February 08, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [February 04, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 31, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 29, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 25, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 22, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 19, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 15, 2022]
WSP : Construction Progress Report from Water System and Public Latrine [January 11, 2022]
Note:
- Construction progress reports are in accordance with technical analysis
- Financial Report will be submitted by other WSP team
- All documents have been authorized by the relevant parties
- Documents in the form of photos or writing must have permission from World Smile Project team
Cc : @pennsif @el-nailul @heriadi @irawandedy @miftahuddin @sofian88 @mariana4ve @bien
Thanks
@klen.civil
Осталось совсем немного! Поздравляю!
Laporan sangat bagus dengan capaian kemajuan yang akurat detail dan terupdate bukti transparansi yang sangat baik :)
Wah udh selesai ya pembangunan nya, warna nya keren. Thanks for.update 😊
Tinggal menunggu pemasangan atap kak
Oh yaya..ntar biru jg ya atap nya
Ya atap ny biru juga
hehehe
👍👍
😇😇